From: Sustainable Energy Advantage, LLC
Sent: Wednesday, August 7, 2024 3:57 PM
To: Sustainable Energy Advantage, LLC
Subject: SEA Eyes and Ears Weekly Flash - New York No. 24-12 - March
25, 2024
SEA's up-to-date online Legislative Tracking Spreadsheet for New York can be found here.
This spreadsheet tracking tool is designed to keep subscribers informed of legislative activity by indicating the most recent dates of legislative action, the next potential legislative action, a short summary, as well as a direct link to the bill docket to learn more.
Please contact Andrew Lidington with any questions regarding New York legislative tracking.
In December 2022, the New York State Department of Public Service (DPS) and the New York State Energy Research and Development Authority (NYSERDA) jointly filed, with the New York Public Service Commission (PSC), the New York’s 6 GW Energy Storage Roadmap: Policy Options for Continued Growth in Energy Storage (2022 Roadmap), which called for a new Indexed Storage Credit for bulk storage procurement and expanding existing retail and residential programs. An overview of the 2022 Roadmap’s key provisions is available in NY Flash 23-1.
On March 15, 2024, in Case 18-E-0130, DPS and NYSERDA submitted an updated Roadmap reflecting increased cost estimates for the residential, retail, and bulk storage program. The table below details programmatic cost estimates from the 2022 Roadmap as well as the recent update.

DPS and NYSERDA attributed their increased estimates to a “material increase
in costs due to factors such as inflation and wholesale capacity price
forecasts.” DPS and NYSERDA expect to issue a request for public comments on
the updated Roadmap in “the coming weeks.”
As last discussed in NY Flash 24-9, on November 27, 2023, NYISO finalized its suite of capacity accreditation related proposals. The proposals are intended to improve NYISO’s modeling of different resource types to more accurately quantify various resources’ contributions to maintaining resource adequacy. On March 4, 2024, NYISO provided final capacity accreditation factor (CAF) values to stakeholders (detailed in NY Flash 24-9).
On March 20, 2024, NYISO provided another presentation to the Installed Capacity (ICAP) working group (see agenda) to highlight incremental tariff revisions to accommodate NYISO’s capacity accreditation reforms and to discuss the data submittal requirements that NYISO plans to impose when collecting operational data from ICAP suppliers. Specifically, NYISO proposed to allow ICAP suppliers to submit their MW-level operational data for the 2025/2026 capability year starting on March 20, 2024, so that final participation elections can be made by August 1, 2024. NYISO is seeking the following information from ICAP suppliers:
Moreover, NYISO noted that data submitted for preliminary NYISO review prior to August 1, 2025, must be confirmed after August 1, 2025, to meet the December 1, 2025, data submission requirement for the 2025/2026 Capability Year.
It is not currently clear what the next steps are on this topic; NYISO
highlighted that questions on this topic can be directed to ntubbs@nyiso.com.
![]()
At the joint Electric System Planning Working Group (ESPWG), Transmission Planning Advisory Subcommittee (TPAS), and Load Forecasting Task Force meeting on March 21, 2024 (agenda here), NYISO gave a presentation providing a status update on the New York City (NYC) Public Policy Transmission Need (PPTN) process.
As discussed in NY Flash 23-25, on June 22, 2023, in Case 22-E-0633, the New York Public Service Commission (PSC) announced that it had issued an Order to establish a new PPTN to interconnect at least an additional 4,770 MW of offshore wind into the New York City (NYC) area, i.e., NYISO Zone J. The PPTN and the offshore wind, together, would facilitate reaching the State’s 9 GW of offshore wind by 2035 target, established by the Climate Leadership and Community Protection Act (CLCPA). In the Order, the PSC directed NYISO to initiate a solicitation for projects to address this PPTN. Under the solicitation, projects selected are required to come online by January 1, 2033, and should be complete “end-to-end” solutions including both offshore and onshore components.
In its presentation, NYISO provided a high-level example of a Viability and
Sufficiency Assessment for a notional project. NYISO also provided updates to
the evaluation and selection criteria that it will consider in its assessment
of projects, in particular regarding project impact on operating reserves.
NYISO also provided updates on project data submission forms and requests.
NYISO noted that the
solicitation window will open April 4 and close June 4. NYISO
noted that it intends to open the window by posting a solicitation letter to
its website and notifying developers via email. Parties that are interested in
being added to the distribution list should email Kirk Dixon, kdixon@nyiso.com, or check the NYISO’s
website for updates.
On March 21, 2024, the Electric System Planning Working Group (ESPWG), Transmission Planning Advisory Subcommittee (TPAS), and Load Forecasting Task Force (LFTF) held a joint meeting (agenda here), at which NYISO provided updates for electric vehicle (EV) energy demand forecasting & analysis as well as building electrification demand and electric heating adoption assumptions.
NYISO gave a presentation on building electrification assumptions, discussing heat pump load, comparing air source heat pumps (ASHP) to gas furnaces, and a possible need for additional supplemental heat in cold climates.
NYISO also gave a presentation on EV forecasting, discussing their EV forecast methodology, EV sales and stock forecasts, and energy demand forecasts. See the below table for a summary of preliminary estimates:
As last discussed in NY Flash 24-10, NYISO has been finalizing its FERC Order 2023 compliance approach. As detailed in NY Flash 23-31, Order 2023 requires independent system operators (ISOs) and regional transmission organizations (RTOs) to transition to a first-ready, first-served cluster study process, and implements a number of changes to the large-scale facility interconnection process designed to increase the speed and certainty of the process. We detailed NYISO’s most recent (March 1, 2024) compliance plan in NY Flash 24-10.
On March 15, 2024, NYISO provided an updated presentation to the Interconnection Issues Task Force (see agenda) to summarize NYISO’s compliance plan and associated tariff revisions necessary to accommodate NYISO’s compliance plan. The presentation also highlighted NYISO’s proposed revisions to its compliance plan updated since its March 1 plan. We summarize key changes from NYISO’s previous compliance plan as follows:
Looking ahead, NYISO plans to submit its Order 2023 compliance package to
FERC by the April 3, 2024, filing deadline.
![]()
On March 15, 2024, in Case 18-E-0130, the New York Public Service Commission (PSC) issued an Order directing Central Hudson Gas & Electric Corporation (Central Hudson), New York State Electric & Gas Corporation (NYSEG), Niagara Mohawk Power Corporation d/b/a National Grid (National Grid), Orange and Rockland Utilities, Inc. (O&R), and Rochester Gas and Electric Corporation (RG&E) (the Indicated Utilities) to file a proposal outlining proposed modifications to their Dynamic Load Management (DLM) Programs. As detailed in NY Flash 20-39, DLM is a demand response program in which distributed energy storage resources can participate. The PSC’s December 2018 Energy Storage Order required the IOUs to develop competitive DLM procurements, with contract terms of at least three years (“Term-DLM”), to supplement the existing tariff-based DLM programs. The Order also required the utilities to develop a premium, “Auto-DLM” program with higher performance requirements. As discussed in NY Flash 23-31, on August 1, 2023, the Indicated Utilities filed a Petition to modify procurement requirements under the Term-DLM and Auto-DLM Programs. The Indicated Utilities noted that the programs’ currently employed “sealed-bid, pay-as-bid” procurement structure has resulted in little to no participation and argued that some flexibility in the DLM model would lead to more participation in the programs.
In the Order, the PSC found that modifications to the Term-DLM and Auto-DLM Programs are appropriate, but that the Indicated Utilities’ proposal lacked details regarding what alternative procurement mechanism or mechanisms should be employed and how the Indicated Utilities would determine which alternative procurement mechanism could be more successful. The PSC directed the Indicated Utilities to file a supplemental proposal outlining the proposed alternative procurement mechanisms, either jointly or individually, by June 7 (within 60 days of the Order).
We note the Indicated Utilities differ from the “Joint Utilities” in that
the Joint Utilities include the Indicated Utilities and Consolidated Edison
Company of New York, Inc. (ConEd). We also note that ConEd filed a separate Petition
for modifications to its DLM Program on November 15, 2023, and the PSC has yet
to issue on Order regarding ConEd’s Petition.
As first introduced, NYISO considers its System and Resource Outlook (SRO) a key component of its biennial Comprehensive System Planning Process. NYISO’s key objectives of its 2023-2042 SRO include (i)‑completing a 20-year projection of system conditions for demand, generation, and transmission across New York; (ii) identification and assessment of congestion elements; and (iii) development of scenarios and performance of analyses to inform internal and external stakeholders.
In previous Flash Updates, we discussed NYISO’s introduction of the project (NY Flash 23-25); benchmarking tasks, study improvements, and high-level assumptions (NY Flash 23-29); scope, timeline, preliminary assumptions, and alternative scenarios (NY Flash 23-34); Base Case, Contract Case, and Policy Case assumptions (NY Flash 23-38); preliminary Base Case results (NY Flash 23-44); final Base Case results (NY Flash 23-48); preliminary Contract Case results (NY Special Flash 23-50.1); final Contract Case results (NY Flash 24-4); and a Contract Case sensitivity and an overview and certain assumptions of the Capacity Expansion Model (NY Flash 24-8).
On March 21, 2024, at a joint meeting of the Electric System Planning Working Group (ESPWG), Transmission Planning Advisory Subcommittee (TPAS), and Load Forecasting Task Force (LFTF) (agenda), NYISO presented an update on the 2023-2042 SRO. Specifically, NYISO provided preliminary results for the Lower Demand, Higher Demand, and State Scenarios, which are all variations on the Policy Case using the Capacity Expansion Model. NYISO also refers to these as the “capacity expansion scenarios.” Key findings included that:
NYISO also noted several updated assumptions for the State Scenario (also listed in this March 15 Memorandum), including that:
For next steps, as explained in the presentation, NYISO intends to continue
its renewable pockets analysis, which evaluates transmission constraints
affecting future renewable generation buildout across several defined
geographic areas (i.e., pockets) for the year 2030 (as discussed in NY
Flash 24-8). NYISO also intends to continue development of the Policy Case
in the Production Cost Model, which includes converting zonal results from the
capacity expansion scenarios to nodal generator placement. NYISO details the
methodology for doing so in its update.
On March 14, 2024, the New York Public Service Commission (PSC) announced that it issued Orders Granting Certificate of Public Convenience and Necessity (CPCN) for two projects, Canisteo Wind (Case 23-E-0297) and the Homer Solar Energy Center (Case 23-E-0412).
Canisteo Wind is a proposed 290 MW project under development by Invenergy. Invenergy intends for the facility to be operational in 2026. Canisteo Wind was selected in the 2018 Renewable Energy Standard RFP (RESRFP18-1) by the New York State Energy Research and Development Authority (NYSERDA) but opted instead to accept a long-term contract with the New York Power Authority (NYPA). The project is also one of 23 projects included in the resource portfolio that the Clean Path NY (CPNY) Tier 4 transmission project will deliver (as discussed in NY Flash 21-47).
Homer Solar Energy Center is a proposed 90 MW solar project under development by EDF Renewables (EDF) in the Towns of Homer, Cortlandville, and Solon, all in Cortland County. EDF intends for the facility to be operational in 2026. As discussed in NY Flash 21-2, in September 2019, EDF initiated the siting process for the project with the New York Board on Electric Generation Siting and the Environment (the Siting Board) under Article 10 but transferred to the ORES’ 94-c process in January 2021. Homer Solar Energy Center was previously selected in NYSERDA’s RESRFP20-1, but subsequently cancelled its offtake contract and rebid into NYSERDA’s accelerated RESRFP23-1 (results expected in April; as discussed in NY Flash 24-9).
We note that the CPCN process is distinct from the aforementioned siting
permit process but is a necessary part of the siting process and pertains to
construction approval: developers can elect to pursue a CPCN contemporaneously
with the siting permit process, or after a siting permit has been granted.
On February 6, 2024, in Docket 21-02553, the New York Office of Renewable Energy Siting (ORES) issued a Decision granting a Motion to Dismiss filed by the Town of Copake (the Town) and denying the application for siting permit filed by Hecate Energy Columbia County 1 LLC (Hecate Energy) for its Shephard’s Run project, a 42 MW photovoltaic solar facility. As reasoning for the Decision, ORES noted that the project had lost its land use rights. Shepherd’s Run started Article 10 review process in January 2020 and later filed to transfer to Section 94-c approval process in May 2021 (as discussed in NY Flash 21-40). ORES issued a Notice of Complete Application (NOCA) for the project on August 25, 2023.
On January 2, 2024, the Town filed a motion to dismiss the project application, with evidence showing that the land lease agreement between Hecate Energy and a landowner had expired on September 17, 2023, and that 20% of the project’s land parcels were sold to another landowner. The Town argued that due to the end of the lease agreement, and because project amendments are prohibited after issuance of a NOCA, the current project proposal is no longer feasible and Shepherd’s Run project needs a project redesign. Therefore, the Town argued the project application should be dismissed without prejudice. On January 4, 2024, the assigned Administrative Law Judge (ALJ) denied the Town’s motion to dismiss, and the Town appealed. ORES staff filed comments partially supporting the Town’s claim for motion to dismiss. ORES staff agreed with the Town that the loss of land use rights could have a substantial impact on the proposed project, but agreed with the ALJ that the issues determination procedure is the appropriate venue to resolve the issues the Town raises. Hecate Energy argued that it was in the negotiation process with the former landowner after the lease expired, and it did not acknowledge the sale of the parcels until the Town filed for motion to dismiss on January 2, 2024. Hecate Energy requested ORES to file a Notice of Incomplete Application instead of granting a motion to dismiss.
As a result of the Decision, Hecate Energy will be required to submit a new
application for the proposed project once it either secures the relevant land
use rights or redesigns the project.
![]()
On March 15, 2024, the New York Department of Public Service (DPS) announced the launch of the Electric Vehicle (EV) Infrastructure Interconnection Working Group (EVIIWG). The EVIIWG was formed to (listed verbatim):
The EVIIWG will hold its first meeting on April 4, 2024, 1:30-4 PM EST. Meeting
registration information can be found here.
As discussed in NY Flash 24-10, in Case 23-E-0070, the Medium and Heavy-Duty (MHD) Electric Vehicle Charging Infrastructure Proceeding, the New York Public Service Commission (PSC) held the following two virtual stakeholder workshops, hosted by the New York Department of Public Service (DPS), the New York City Department of Transportation (NYC DOT), and the New York City Economic Development Corporation (NYC EDC).
At the workshops, DPS Staff provided an overview of the MHD proceeding, and
NYC DOT and NYC EDC provided an overview of their Smart Truck Electrification
and Freight Decarbonization Feasibility Study and findings. Each workshop had a
different focus, as noted above, and the workshops included stakeholder
participation.
![]()
On March 15, 2024, Governor Kathy Hochul announced $16 million of available funding to be administered by the New York State Energy Research and Development Authority (NYSERDA) to advance innovation in clean hydrogen. This funding aims to support the following:
This funding is available through the Hydrogen and Clean Fuel Program, which includes two solicitation opportunities:
![]()
On March 14, 2024, the New York Power Authority (NYPA) announced
that it is seeking bids to develop an up to 6 MW community solar project paired
with up to 3 MW of battery energy storage on the State University of New York
(SUNY) Niagara Community College campus in Sanborn, NY. Bids are due April 17
and should be submitted to kylie.murphy@nypa.gov.
Bids will be evaluated based on technical competency, implementation approach,
strength of management team, price, risk analysis, and schedule for project
delivery and completion.
As discussed in NY Flash 23-1, on December 23, 2022, in Docket ER23-729, PJM Interconnection LLC (PJM) submitted an Emergency Request requesting that FERC allow it to, during the Base Residual Auction (BRA) process, exclude resources from a Local Delivery Area (LDA) reliability requirement if units do not bid into the auction as modeled during its reliability planning. PJM explained that in conducting the 2024/2025 BRA, a significant amount of planned generating capacity resources, which were expected to participate in the auction based on the in-service date of the resources’ interconnection agreements, did not ultimately offer into the auction, despite being included in the LDA reliability requirement. As a result, the increased reliability requirement artificially inflated the prices in the Delmarva Power South LDA, which PJM argued was unjust and unreasonable.
As discussed in NY Flash 23-9, on February 21, 2023, FERC issued an Order accepting the Emergency Request with an effective date of December 24, 2022, such that it would be applicable to the 2024/2025 BRA (meaning that the rules would change mid-auction) and future BRAs. FERC reasoned that the rule change would help PJM ensure that load-serving entities are charged for capacity based on an LDA Reliability Requirement that reflects actual reliability needs. FERC asserted that its decision did not violate the “filed rate doctrine,” a legal principle that prohibits retroactive ratemaking.
On March 12, 2024, the U.S. Court of Appeals for the Third Circuit vacated
FERC’s February 21 Order as it applies to the 2024/2025 BRA (but not as it
applies to future BRAs), finding that the Order did violate the filed rate
doctrine.
On March 12, 2024, in Docket ER23-2917, FERC issued an Order Accepting Proposed Tariff Revisions which authorize California Independent System Operator Corporation (CAISO) to implement the Subscriber Participating Transmission Owner (PTO) model for its Open Access Transmission Tariff.
In the proposal filed by CAISO on September 22, 2023, CAISO explained that the revision would enable the transmission projects outside the CAISO balancing authority area (BAA) to facilitate delivery to CAISO. As a result, transmission project developers could join CAISO without going through the CAISO transmission planning process. The revisions will establish a new revenue model for transmission project developers. Under the current tariff, participating transmission owners (TOs) receive transmission revenue through CAISO’s Transmission Access Charge (TAC), which charges all ratepayers. The revision will allow PTOs to receive revenue from subscribers separate from TAC process, in which the participating transmission projects only receive fundings from subscribers. Non-subscribers will have to pay for their share for using the subscribers’ PTO facilities.
Some stakeholders objected to the proposed non-subscribers’ rate paying for using the subscribing PTO lines, which they argued that the proposal would be hard to implement and would inevitably increase the bills for ratepayers. CAISO argued that the original costs of constructing subscribing PTO facilities will be excluded from TAC, therefore it largely won’t impact ratepayers.
Commissioner Allison Clements issued a Concurring
Statement in support of the Order, noting that the revision will enhance
grid’s reliability and lower transmission and distribution costs in CAISO.
However, Commissioner Clements also noted that there is not enough evidence and
research showing the proposed hybrid cost allocation tariff is just and
reasonable for all stakeholders and she encouraged FERC and stakeholders to
continue explore and study the proposed fee structure.
![]()
On March 15, 2024, the Bureau of Ocean Energy Management (BOEM) announced that it would conduct an environmental review of the Atlantic Shores North offshore wind project, to be sited approximately eight miles off of the New Jersey coast in lease area OCS–A 0549. On March 18, BOEM published a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) for the Project. Atlantic Shores North is proposed by developer Atlantic Shores Offshore Wind, LLC, a 50/50 joint venture between EDF Renewables and Shell New Energies. According Atlantic Shores North’s Construction and Operations Plan (COP), the project will consist of a maximum of 157 wind turbines (potentially up to approximately 2,300 MW, assuming 15 MW turbines).
Atlantic Shores North does not currently have an offtake agreement. Atlantic Shores South (the collective name of the Atlantic Shores Offshore Wind Project 1 and the Atlantic Shores Offshore Wind Project 2) is another project under development by the same developer, in lease area OCS-A 0499. As discussed in NY Flash 21-26, in 2021, Project 1 was selected by the New Jersey Board of Public Utilities to provide 1,510 MW.

As part of the EIS scoping process, BOEM will accept public comments that focus on identifying reasonable alternatives, potential mitigation measures, and other issues of concern. Comments may be submitted through Docket No. BOEM-2024-0008 on the Regulations.gov website and will be accepted through May 2.
In addition, BOEM has scheduled a series of scoping meetings. The meetings are scheduled for the following dates and times (all times ET):
Virtual meetings:
In-Person meetings:
On March 14, 2024, Monitoring Analytics LLC (Monitoring Analytics), the Independent Market Monitor for PJM Interconnection LLC (PJM), released its 2023 State of the Market Report for PJM (Report). According to the Report, Monitoring Analytics estimates between 24 and 58 GW of thermal resources are at risk of retirement through 2030, including 4.3 GW of announced retirements, 19.6 GW of retirements due to state and federal environmental regulations, and 33.6 GW of retirements for economic reasons (i.e., “based on expected forward prices”).
Critically, Monitoring Analytics asserts that there is “no clear source of replacement capacity” because while renewables “can replace a significant amount of the energy output” the “retiring capacity can only be replaced by gas fired or dual fuel generation,” for which new capacity is constrained by the limitations of the existing gas pipeline system and is not adequately represented in the PJM interconnection queue.
Monitoring Analytics thus made several recommendations, including that PJM:
On March 15, 2024, the Regional Greenhouse Gas Initiative (RGGI) announced the results of its 63rd carbon dioxide (CO2) allowances auction. RGGI reported that 24,272,157 allowances, which includes the 8,416,278 Cost Containment Reserve (CCR) allowances, were sold at a record high clearing price of $16.00/ton (a 7.5% increase from the 62nd auction, which cleared at $14.88/ton, as discussed in NY Flash 23-50). Bids ranged from $2.56 to $25.00 per allowance. CCR allowances were sold by RGGI states when the clearing price reached $15.92. $388.4 million was raised in total for states to reinvest. Though they have not always done so, states have primarily invested auction proceeds in strategic programs including energy efficiency, renewable energy, bill assistance, and greenhouse gas (GHG) emission abatement programs.
Virginia and Pennsylvania Participation
As discussed in NY
Flash 24-3, Virginia is no longer a RGGI participating state and thus did
not participation in the 63rd auction, and Pennsylvania’s
participation is currently under appeal to the Pennsylvania Supreme Court as it
was barred from offering allowances by a lower court (as discussed in NY
Flash 23-45). As discussed in NY
Flash 24-11, Pennsylvania may withdraw from RGGI regardless of a successful
appeal to institute its own GHG cap-and-invest program.
On March 21, 2024, the U.S. Department of Energy announced the release of the National Renewable energy Laboratory’s Atlantic Offshore Wind Transmission Study. The two-year study investigated the transmission options to enable offshore wind development across the Atlantic states. A map of the three proposed transmission scenarios is shown below.
Key findings from the Study are listed below (listed verbatim):
As part of the study a wide variety of factors were considered including expansions to offshore wind capacity out to 2050; cost-benefits of different transmission technologies; operational, environmental, reliability aspects of different transmission topologies sub-station and cable costs; environment and ocean co-use concerns; among others. The authors emphasized that the feasible transmission corridors identified in the study are to highlight the possibility of interconnected offshore transmission only and further analysis is needed completed for actual site identification.
The study did not present a favored alternative, but instead suggested a phased approach that can efficiently take advantage of infrastructure development capabilities. One example of this phased approach is shown in the graphic below. The study did, however, note that “defining a common interoperability standard before HVDC is deployed in topologies like the interregional scenario will be critical to meeting the development timelines and achieving the benefits quantified in this study.”

Answers to frequently asked questions regarding this study and developing
offshore transmission overall are available on the study website.
This study also informed the An
Action Plan for Offshore Wind Transmission Development in the U.S. Atlantic
Region (last discussed in NY
Flash 23-38).
On March 13, 2024, the U.S. Department of Energy announced funding for 52 hydrogen projects totaling $750 million. These projects will “help advance electrolysis technologies and improve manufacturing and recycling capabilities for clean hydrogen systems and components, directly supporting more than 1,500 new jobs.” A full breakdown of the projects is available here. We summarize the projects in ISO-NE, NYISO, and the PJM Interconnection regions below:
On March 20, 2024, the U.S. Department of the Interior (DOI) announced its recommendation for a second offshore wind sale in the Gulf of Mexico. The offshore wind sale for the gulf of Mexico was held on August 29, 2023 (discussed in NY Flash 23-29). In parallel to the DOI announcement, the Bureau of Offshore Energy Management (BEOM) has published Public Sale Notice in the Federal Register (Docket No. BOEM-2024-0017). BOEM has proposed four lease areas for sale, as shown in the table and map below.


Additional maps and material, such as the forms to become a qualified bidder, are available on BOEM’s Gulf of Mexico website. BOEM is seeking public comment on the prosed sale, with particular interest in stakeholder feedback on the following topics:
Comments are due May 20, 2024.
Also of note, BOEM plans to use new auction software and as a result there
will be changes to the previous auction rules. Before the final sale, BOEM will
host a mock auction for qualified bidders to ask questions and become familiar
with the new software. Information on the revised auction procedure can be
found here.
![]()
Best regards,
The SEA Team

Sustainable Energy Advantage, LLC
John Keene - Senior
Director
Tel. 508-665-5870 | jkeene@seadvantage.com
www.seadvantage.com
![]()
Connect with SEA!
Eyes & Ears Terms
and Conditions
Eyes & Ears Service is provided to the Subscriber for the Subscriber’s
internal use only, and may be distributed to employees, officers and directors
of Subscriber or Authorized Affiliate who have been made aware of the
Limitations on Use under the Subscription Agreement. Subscriber agrees not to
distribute materials received under the Eyes & Ears Service, whether by
written, oral or electronic means, to any other person, including consultants
engaged by Subscriber, except with specific written permission from SEA or as
required by applicable law, regulatory proceeding or exchange rule. Subscriber
is subject to additional terms and conditions stated in the Subscription
Agreement.