PUC issues PATER Study Phase 1 Report; Public meeting on Oct. 7, comments due Oct. 14

On September 29, 2026, in Pennsylvania Public Utility Commission (PUC) Docket No. M-2026-3059601, KeyLogic LLC (KeyLogic) and the Electric Power Research Institute (EPRI) submitted their Phase 1 Report for the Pennsylvania Accelerated Transmission and Energy Redevelopment (PATER) Study.

Pursuant to the PUC’s February 19 Order, the PATER Study is intended to “assess … retired electric generation facility sites as well as existing and needed transmission improvements to improve resource adequacy and increase generation capacity and capability.” The Phase 1 (also referred to as Part A) Report identifies a portfolio of 21 candidate “deactivated energy sites” that are suitable for redevelopment, including to site new generation and large load. The Phase 2 (Part B) Report will include more comprehensive analysis and narrow candidates to the most promising 5-7 sites.

The 21 candidate sites are shown in the figure below:

According to the PUC’s September 23 Secretarial Letter, the PUC will hold a public meeting on the Phase 1 Report on October 7 at 9:30 am in Hearing Room 1. The meeting is open to the public via livestream. Additionally, the PUC invited comments on the Phase 1 Report, due October 14.