PSC postpones Tier 4 solicitation release date from December 14 to January 29
On December 11, 2020, the New York State Energy Research and Development Authority (NYSERDA) filed a Request for Extension of Time with the Public Service Commission (PSC) in Case 15-E-0302, seeking to postpone NYSERDA’s Tier 4 Renewable Energy Standard (RES) procurement release date from December 14, 2020 to January 29, 2021. As discussed in Flash Update 20-42, the PSC issued an Order Adopting Modifications to the Clean Energy Standard on October 15, 2020 that approved several changes to the Clean Energy Standard (CES), including directing NYSERDA to issue a solicitation for renewable energy deliveries into New York City (Tier 4 resources). NYSERDA indicated in its Request that the additional time would help NYSERDA and Department of Public Service Staff to make the solicitation successful.
Also on December 11, the PSC issued a Ruling on Extension Request, approving NYSERDA’s Request as-written.