IPA Index REC RFP announcement; Supplier Fees, Guidelines on Contract Execution Process, and initial Index Values Index(t) for the Strike Price Adjustment Mechanism

The Illinois Power Agency (IPA) recently issued two announcements relating to the 2025 Indexed REC RFP. The first announcement provided the component values that will be used to adjust the strike price for bids that opt into the one-time Strike Price Adjustment Mechanism. As discussed in PJM Flash 25-23, this price adjustment mechanism is an opt-in, one-time, formula-based adjustment to the REC price, post-contract negotiation, to account for changes in different project cost components due to inflation between the date of the project bidding into the solicitation and a later adjustment date to be defined. The full calculation for determining the adjustment is available in Exhibit G of the Final Indexed REC Contract. The tables below show the component adjustment values.

The second announcement provided the calculation of the Supplier Fee for selected bids. The Supplier Fee is equal to $0.90 times the annual amount of RECs sold and is due within seven days of the IPA approval of the bid. The IPA also noted it can provide a full summary of the contracting process upon request.

The 2025 Index REC RFP bid window opens on August 1, from 10:00 am CT to 12:00 pm CT.