Final FY2022 budget negotiations concluded, budget bills sent to Governor for signature; final budget includes tax standardization and new labor requirements for renewable energy projects, a new Farmland Protection Working Group, and the Environmental Bond Act of 2022, but does not allow for deduction of RECs for NYC buildings

On April 7, 2021 the New York State Senate and Assembly voted to approve the final package of Fiscal Year (FY) 2022 Article VII budget bills and sent the bills to Governor Cuomo for his signature. As the executive branch was heavily involved in negotiating these final bill versions, it is expected the Governor will sign the entire package of bills to enact the state budget, about 1 week past the April 1 due date. As discussed below, the final budget includes many notable provisions related to renewable energy. We note that some of these provisions were moved from their original proposed Article VII bills (most recently discussed in Flash Update 21-10), into different Article VII bills, which are specified below.

Highlights of the legislative amendments to the Governor’s budget proposal include:

  • Standardized tax assessment and new labor requirements for renewable energy projects passed
  • The Governor’s proposal to allow NYC buildings to deduct Tier 2 RECs, Tier 4 RECs, or ORECs from their emissions regarding Local Law 97 was omitted
  • Technical changes to 94-c (including exempting projects from SEQRA); and the establishment of a Farmland Protection Working Group relating to renewable energy development passed
  • Alle-Catt Wind Farm may now be granted easements on designated public lands, with conditions
  • The Environmental Bond Act was established and will be voted on in the 2022 general election (changed from 2021 to 2022 potential enactment)

We provide a more detailed summary by provision herein.

Article VII Revenue (REV) Bill :

  • Part X: Standardizes tax assessments for renewable energy projects and requires Industrial Development Authorities to support and promote renewable energy projects
    • Extends the timeline for tax assessment exemptions for wind and solar projects from those constructed prior to 2025 to those constructed prior to 2030. In order to be eligible for tax assessment exemptions, renewable energy projects must now be constructed between 1988 and 2030.
    • Requires taxing jurisdictions that have not removed the tax assessment exemption to notify renewable energy project owners or developers in writing (a law or resolution may suffice as notification) if they intend to require a PILOT contract. Written notification must be provided within 60 days of a project owner or developer notifying the highest ranking official of the taxing jurisdiction of its intent to construct a renewable energy project. If the taxing jurisdiction fails to provide written notice of its intent to establish a PILOT contract within 60 days, the project will not be obligated to make such payments.
    • Requires the assessed value of solar or wind energy systems over 1 MW to be determined by a discounted flow approach that utilizes/requires:
  • An appraisal model to be published by the Department of Taxation and Finance, in consultation with NYSERDA, within 180 days of the effective date of this law (and updated periodically);
  • A discount rate or rates published annually by the Department of Taxation and Finance. Rates will be published in preliminary form with at least 60 days public comment before publishing final rates; and
  • The Department of Taxation and Finance to consult with the New York State Assessors Association in formulating the model and discount rate(s).
    • Adds renewable energy development to the set of state policy goals that are to be supported and promoted by Industrial Development Authorities (IDAs).

We note that property tax assessment standardization is likely to have a material impact on project development, as it will establish a clear process for establishing acceptable PILOT payment levels and set predictable bounds around the size of those PILOT payments. The standardized assessment law is meant to address instances where PILOT negotiations with local taxing authorities become time- and resource-intensive, thereby creating obstacles to meeting project milestones.

  • Part TT (previously Part AAA of TED bill, Senate version): Authorizes the Environmental Bond Act of 2022
    • Authorizes $3 billion in state debt to create the “Environmental Bond Act of 2022 ‘Restore Mother Nature’”
    • Requires that, in order to take effect, a proposition or question therefor must be voted on and approved by the people of New York in the November 2022 general election.
  • Part UU (previously Part BBB of TED bill, Senate version): Establishes the Environmental Bond Act of 2022
    • Amends Environmental Conservation Law and State Finance Law to implement the $3 billion Environmental Bond Act of 2022 “Restore Mother Nature.”
      • Not less than $1 billion for restoration and flood risk reduction;
      • Up to $550 million open space land conservation and recreation;
      • Up to $700 million for climate change mitigation; and
        • Not less than $350 million of climate change mitigation funds available for green building projects, which include projects that increase energy efficiency or the use or siting of renewable energy on state-owned buildings or properties including buildings owned by the State University of New York (SUNY), the City University of New York (CUNY), and community colleges.
      • Not less than $550 million for water quality improvement and resilient infrastructure.

We note this proposal is very similar to the “Environmental Bond Act of 2020 ‘Restore Mother Nature’” that was passed in last year’s budget negotiations (discussed in Flash Update 20-14), however in the 2020 version, the implementation was made contingent on a review of the State’s finances by the New York State Budget Director. In April 2020, after review, Governor Cuomo’s office removed the Environmental Bond Act of 2020 voter referendum from the November 2020 ballot. There is no provision in this year’s version that would allow the Governor or Budget Director to remove the voter referendum from the 2022 election.

Article VII Transportation, Economic Development and Environmental Conservation (TED) Bill:

  • Part W: Authorizes the New York State Energy Research and Development Authority (NYSERDA) special assessment
    • Extends NYSERDA’s special assessment on large gas and electric utilities (>$500k gross revenues) to fund clean energy programs, in the amount of $22.7 million to be collected by September 10, 2021.
      • Directs NYSERDA to transfer up to $4 million to the state general fund for climate change-related services and expenses for the Department of Environmental Conservation (DEC), $150,000 to the state general fund for services and expenses for the Department of Agriculture and Markets, and $825,000 to the University of Rochester Laboratory for Laser Energetics (a scientific research facility commissioned to serve as a center for investigations of high-energy physics, specifically those involving the interaction of extremely intense laser radiation with matter) from the funds received; and
      • Directs NYSERDA to provide an itemized record to the Chair of the Public Service Commission (PSC) on August 1 of each year detailing any and all expenditures and commitments ascribable to funds received as a result of this assessment.

Article VII Education, Labor and Family Assistance (ELFA) Bill

  • Part AA: Extend prevailing wage to covered renewable energy projects greater than 5 MW
    • Establishes prevailing wage requirements for construction, engineering, and consulting work on renewable energy projects that involve the procurement of RECs by a public entity or on behalf of a public entity.
      • Applies to projects over 5 MW capacity. The provisions do not apply to construction performed under an enforceable agreement between a project owner or contractor and a bona fide labor organization.
    • As a condition to any REC agreement, the owners of renewable energy projects must stipulate to the contracting public entity that they will enter into a labor peace agreement with at least one bona fide labor organization that is actively engaged in representing or attempting to represent employees who provide necessary operations and maintenance services for renewable energy projects, excluding seasonal and temporary employment not otherwise necessary for the actual maintenance of the project. The maintenance of a labor peace agreement will be an ongoing material condition of any continuation of payments under a REC agreement.
      • “Labor peace agreement” means an agreement between an entity and labor organization that, at a minimum, protects the state’s proprietary interests by prohibiting labor organizations and members from engaging in picketing, work stoppages, boycotts, and any other economic interference with the relevant renewable energy project.
    • Each owner and developer of a covered renewable energy system over 5 MW must comply with the objectives and goals of certified minority and women-owned business enterprises (as defined in Article 17-b of NYS Executive Law). The Department of Labor will provide training for these enterprises on renewable energy systems.
    • Any contract for construction, reconstruction, alteration, repair, improvement, or maintenance that involves a REC agreement must include a provision that the iron and structural steel used or supplied in performance of the contract must be made in whole or substantial part within the United States.
      • Provision does not apply to equipment purchased prior to effective date of this law (October 1, 2021).
      • Includes steel or iron permanently incorporated into public works and includes from the initial melting stage through application of coating except metallurgical processes involving the refinement of steel additives. Iron and steel products that are capable of being moved from one location to another are not considered “permanently incorporated” into a public work.
    • The head of the Department of Public Service (DPS), under his or her sole discretion, may give “significant consideration” to the procurement of equipment and supplies located within New York State in the evaluation process of competing bids for public works.
    • Any changes to public procurement processes must be paired with simultaneous recommendations to legislative leadership regarding necessary changes to this provision, if any, in meeting the legislative intent of this provision.
    • Proposed requirements take effect October 1, 2021 and apply to renewable energy projects (above 5 MW) awarded a contract issued by the state on or after that date.

We note that NYSERDA’s solicitations have already required payment of prevailing wage, however, the requirement to enter into a labor peace agreement, comply with women and minority owned business goals and objectives, and to source materials from within the U.S. are new proposals that are likely to impact most, if not all, renewable energy projects over 5 MW with REC contracts awarded by the state.

Article VII Public Protection and General Governance (PPGG) Bill:

  • Part AAA: Authorizes the grant of certain easements to Alle-Catt Wind Energy LLC
    • Authorizes the DEC to grant easements, which meet certain conditions, for buried electrical cables on a portion of real property within the Farmersville State Forest, Swift Hill State Forest, and Lost Nation State Forest in the county of Allegany.
      • 18-months after the project ceases operation, the easements will revert back to the DEC.
      • Easements are contingent on the issuance of a Certificate of Environmental Compatibility and Public Need (CECPN) pursuant to Article 10. We note that, as discussed in Flash Update 20-23, a CECPN was granted to Invenergy for the Alle-Catt Wind project in June 2020.
    • Easements will be granted to Alle-Catt Wind Energy LLC for fair market value plus 20%, plus $100,000 each. Monies received will be deposited into the State Environmental Protection Fund, and eventually used to obtain real property for open space purposes as defined in the State’s Open Space Conservation Plan.
    • Takes effect immediately and expires after 5 years (easements expire according to their terms).
  • Part BBB (previously Part Q of TED bill): Technical changes to the Accelerated Renewable Energy Growth and Community Benefit Act
    • Establish that projects seeking approval under the new 94-c permitting regime are excluded from SEQRA requirements (same exclusion provided to Article 10 projects).
    • Broadens the language giving Office of Renewable Energy Siting (ORES) the ability to assess fees for the purpose of recovering costs ORES incurs.
    • Amends the definition of “alternative energy production facility” from projects with a capacity of up to 80 MW to a capacity of less than 25 MW.
    • Establishes a Farmland Protection Working Group within the executive branch composed of the Commissioner of Department of Agriculture and Markets; the Commissioner of the DEC; the Executive Director of ORES; the Commissioner of the Department of Public Service (DPS); the President of NYSERDA; local government officials or representatives from municipal organizations; representatives from at least two county agriculture and farmland protection boards; and other “appropriate stakeholders.”
      • The Working Group must meet three times a year.
      • By April 3, 2021, the Working Group must recommend strategies to encourage and facilitate input from municipalities in the siting process and to develop recommendations that include approaches to recognize the value of viable agricultural land and methods to minimize adverse impacts to any such land resulting from the siting of major renewable energy facilities.
  • Part CCC (previously Part ZZ of TED bill, Assembly version): Extends and increases the “Clean Vehicle Projects” Rebate Program
    • Extends the current rebate program to April 1, 2025 expiry (from 2023) for municipalities to recover costs of any eligible infrastructure projects which support the development of clean vehicles.
    • Increases the rebate amount for eligible electric vehicle purchases from $750-$5,000 to $2,500-$7,500.
    • Provides that eligible infrastructure projects that will maximize access by multiple public users who might otherwise not have access may receive a maximum rebate of $300,000 per facility (maintains $250,000 maximum for other eligible facilities).
    • Defines fast chargers as eligible for rebates.
    • Removes requirement that eligible vehicles must be rated at no more than 8,500 pounds gross vehicle weight.
  • Part DDD (previously Part EE of TED bill): NYSERDA Build-Ready Authorization
    • Amends NYSERDA’s Build-Ready Program to establish that NYSERDA will acquire, sell, and transfer development rights using “single purpose project holding companies established by or on behalf of NYSERDA and having no separate and independent operational control.”

Many budget proposals did not make it into the final budget versions, as noted below. We note that omission of these provisions does not necessarily equate to legislative opposition, as some of these provisions may be taken up in separate legislation throughout the regular Session.

  • TED bill Part R: Deduction of Renewable Energy Credits in New York City – Omitted
  • TED bill Part NN: Increase statutory cap for the Electric Generation Facility Cessation Mitigation Fund – Omitted
  • TED bill Part YY: Directs Emission Allowance Funds to Disadvantaged Communities – Omitted
  • TED bill Part ZZ: Allows Municipalities to Procure Electric Buses and Related Equipment Without Holding a Competitive Auction – Omitted
  • TED bill Part GGG: Requires Public Employees to be on Site, Perform Review, and Make a Determination on Any Projects with Public Contracts – Omitted

The next step in the budget process is for Governor Cuomo to sign the budget bills into law, which is expected imminently (at most within 10 days of being delivered to the Governor).